VOGUEABOVE GROUND SWIMMING POOLINSTALLATION &OPERATING GUIDETHIS BOOKLET CONTAINS THE FOLLOWING INFORMATION:-STAGE 1 - SITE PREPARATION FOR FOR OV
ALL FILTERS ARE NOWSUPPLIED WITH A SIX-WAY MULTIPORT VALVE112.5
12
STAGE 4 - POOL MAINTENANCE & OPERATING GUIDESTEP BY STEP THROUGH THE EQUIPMENTSurface Skimmer-This will be found at the top side of the pool wall
TO BACKWASH THE FILTER.It is a good idea to top the pool up by a couple of inches, as you will be loosing some tobackwash/rinse.IF A ‘ROLL-OUT’ BACKWA
UNDERSTANDING YOUR POOL WATER.Filtered Water. Your pool filtration system has been designed to circulate and filter the whole amount of water within t
VACUUMINGTo enjoy the most out of your pool you not only need to filterand chemically treat the water you also need to physically cleanthe pool of deb
POOL HEATINGPool heating can be achieved using gas- natural and propane, oil, heat pump, heat exchanger- utilising your existing houseboiler, electric
COMMISSIONING YOUR POOL FOR SUMMERWhilst you can employ us to carry out the spring commissioning to your pool it is quite possible with To commission
TROUBLE SHOOTING1. Pool Pump-will not run- check that power is oncheck that RCD (earth trip) & MCB is oncheck that time clock in ‘timed’ or ‘on’ p
INTRODUCTIONThank you for choosing a Vogue Above Ground Swimming Pool. We trust you will have many happy years of pleasure andenjoyment from your inve
DiagonalDiagonalPoolWallFront edgeof T Brace9cm9cm6cmGround LevelTop of Concrete Pad shouldbe no higher than ground level3STAGE 1 - ALTERNATIVE SITE
Note: actual pool size is 19’7” x 12’1” (6.54m x 3.69m) with 6ft (1.83m) radius ends-this will make each end of the poolslightly smaller than the mid
5.00m1.14m1.14m1.14m0.220.223.16m5.91m5.91m1.14m2.285m13mmPoolWall4.54m113cm13cm13cm1.39mBetweenBraces(front edg5.00m1.14m1.14m1.14m0.220.224.11m6.47m
ZENITH 7.11 X 3.66m(23 X 12)ZENITH STEEL POOLS2.86m2.31m3.67m3.67m1.14m 1.14m0.290.293.69m1.39m113cm13cm13cmBetweenBraces(front edge)3.86m1.14m1.14m0
The liner installation is a straight forward procedure as long as you follow the instruction guide lines carefully depicted inthe Vogue Installation m
Place a liner-lock clip onto beading tohold liner in position.Gently heat liner beading with a hairdryer and stretch approximately every2ft and apply
STAGE 3 - FILTER & PUMP INSTALLATION - PLUMBING LAYOUTVOGUE ABOVE GROUND POOL :- PLUMBING LAYOUTSKIMMERPOOLWALLINLETFLOWP/T SOCKETUNIONFLEXIBLE P